For wind turbine project from design and planning to operational use-takes approximately 4-7 years. An offshore wind turbine project requires about 7-10 years.
> For wind turbine project from design and planning to operational use-takes approximately 4-7 years.
That's still better than 11-12 years. How long does a solar farm take?
If residents' opposition is rooted in higher power prices, data centers could just pay extra instead until the new capacity comes online. Seems like a cheap way to pay off opposition.
> An offshore wind turbine project requires about 7-10 years.
Given this article is about Pennsylvania, it'll probably take millions of years.
The famous evening duck curve, when people go home and cook and turn on heating/cooling appliances. California is able to flatten that out with batteries alone.
> Lot of industry, especialy heavy industry, chemical plants are running 24/7.
Right...so they also run during the day (that's what 24/7 means), when everyone else is using electricity. At night they're the only users. Which means less demand at night compared to the day.
> see electricity prices in Europe
This article is about Pennsylvania. That isn't in Europe.
* The longest piece for wind is "Approvals and permits" which takes up to 5 years of the 4-7y.
* The building part "takes approximately 3-6 months" for building wind.
So wind can be built far faster if we're willing to speed up approvals and permitting.
And even if corners are cut for approvals/permitting, the worst case for a wind turbine failure is a lot better than a nuclear failure.
https://jmhpower.com/how-long-does-it-take-to-build-a-wind-t...